Andrew Howard, J.Burke & Associates

Dermot Keating Construction Ltd. was appointed as the Main Contractor under the Summer Works scheme for refurbishment works on Ard Scoil na Deise, Dungarvan in July 2010.

The project involved the replacement of windows and window cills and the application of an external insulation and render system.The project programme was extremely tight, but we are happy to say the DKCL brought the project in on programme and to a good standard of workmanship, and demonstrated good management of its sub-contractors who were directly installing the windows and insulation/render system.

Disruption to the school was kept to a minimum during the project, and good housekeeping was maintained to the satisfaction of the Employer. Communication with the Design team and the Employer was also very good, and DKCL also performed its duties as PSCS to the satisfaction of the PSDP and the relevant Health & Safety regulations.

All snags were attended to in an expeditious manner after practical completion, and the required information for the compilation of the Health & Safety File was handed over thereafter.

In summary, we would have no hesitation in recommending Dermot Keating Construction Ltd. for similar works in the future.

Andrew Howard, J. Burke & Associates, 16th December 2010