Project

Educational

W.I.T Business Building - Block F06-F09

Client:

Waterford Institute of Technology.

Value:

€650,000

Architect:

Tritschler Tritschler & Associates

Quantity Surveyor:

Structural Engineer:

Homan O\'Brien
W.I.T Business Building - Block F06-F09
Background
WIT required the renovation of classrooms which were previously built in the 1970s.

Description of Services
Dermot Keating Construction Ltd (D.K.C.L.) began the project by removing all suspended ceilings, suspended floors, internal joinery, mechanical and electrical applications and demolishing all 225mm dividing block walls.
We built three new classrooms, an office, a cleaner's store and a two storey service duct. All new walls were of 225mm thick blockwork. D.K.C.L. constructed 600mm tassle walls, fitted 4x3 wall plates to same and joisted out all floors with 9x2 joists and covered with WBP. Fitted new suspended ceilings to all rooms. Installation of modern mechanical, electrical, data and fire alarm systems. Fitted all new hardwood joinery and fire doors. Installed all new aluminium doors and windows. Ensured all fire sealing on site.
Internally painted and decorated all areas and laid new carpet tiles throughout the renovation.
Existing blockwork had to be scabbled in order to receive a plaster scratch coat. Applied a scratch coat of plaster and skim to all internal walls. Installed and upgraded the existing drainage network by inserting 225mm pipes under the concrete floors & footpaths and connected into the existing services.
The project was completed by forming fire escape ramps to the rear of the classrooms, fitting of stainless steel handrails to the sides of the sloped ramps.

Key Services Undertaken
  • Demolition
  • Plastering
  • Installation of new windows and doors
  • New build
  • Mechanical and engineering
  • Joinery
  • Fire Sealing
  • Suspended ceilings
  • Decoration – internal and external
  • Floor finishing
  • Drainage
  • Fire escape ramps